How to Compare Elevator Quotations: Scope, Exclusions and a Buyer’s Comparison Worksheet

To compare elevator quotations, first put every proposal against the same technical requirements and division of work. Then record what each supplier includes, excludes, offers separately or leaves unspecified. Compare prices only after identifying technical differences and the costs that still need confirmation.

Three stainless-steel elevator doors in a light stone lobby
Equipment appearance is only one part of the quotation. Compare the written configuration, scope and responsibilities.
Scope

Included, excluded, optional or unspecified.

Technical fit

One agreed requirement and drawing baseline.

Responsibility

Traceable answers and named owners.

In this guide

The useful result is a comparison record that lets your team explain a buying decision. It should show where each answer came from, which questions remain open and who must resolve them. A low total with unresolved installation scope is not yet a complete project budget.

This guide is for buyers who already have written proposals for complete elevators. Use the worksheet below with your project engineer and the parties responsible for local installation. It organizes the decision; it does not establish technical compliance or interpret your contract.

Freeze the reference that every quotation must answer

Create a comparison cover sheet before entering prices. Identify the project, destination, elevator units, current requirement schedule and drawing revision. Record the quotation reference, revision, date and validity for each supplier.

Your reference should identify the configuration that matters to the project: intended use, load requirement, car and entrance dimensions, served floors, travel, power supply, finishes and required functions. Include the applicable project requirements and the documents needed to demonstrate compliance. Use your approved technical information; do not fill an unknown dimension with a convenient assumption.

Where the project is still developing, label the comparison as preliminary and list its unresolved inputs. For example, a quotation based on an earlier shaft drawing may need technical review before its price can be compared with an offer based on the current drawing. A similar product description does not settle that difference.

JAFITA’s elevator and escalator range provides a starting point for the equipment category. Your comparison, however, should follow the specific configuration and documents submitted for your project.

Keep scope, technical fit and responsibility in separate fields

A single tick cannot tell you whether something is supplied, technically suitable and assigned to the correct party. Record those questions separately. This is particularly useful when procurement, engineering and the installation contractor review the same proposals.

Use these scope labels consistently:

Scope labelWhen to use itWhat to record next
IncludedThe quotation explicitly places the item within its quoted scopeSource reference and any stated conditions
ExcludedThe quotation explicitly leaves the item outside its scopeWho will provide it and whether its cost is known
OptionalThe item is offered separately or depends on a selected optionExact option reference, selection decision and additional price if stated
UnspecifiedThe available documents do not settle the itemA clarification question and an owner

In a different field, record technical review as matches the agreed baseline, deviation identified or not yet confirmed. Procurement can collect the documents, but the responsible technical party should decide whether a deviation is acceptable.

Keep the responsibility field equally specific. “By others” is an unresolved handoff until the project identifies the relevant party and that party confirms its scope. It is not a useful substitute for a named installation contractor, buyer responsibility or agreed supplier service.

Build the worksheet around the work your project actually needs

Use a separate set of supplier columns for each proposal. The following rows are prompts for checking the actual agreement; they do not assign a universal responsibility to JAFITA or any other supplier.

Comparison areaQuestions to settle
Equipment configurationWhich requirement and drawing revisions does the proposal follow? Are options and deviations identified?
Car, entrances and finishesAre the specified dimensions, arrangements and finishes covered by the same reference documents?
Controls and interfacesWhich functions and external interfaces are included, and what information must another party provide?
DocumentsWhich drawings, instructions and project-specific evidence will be supplied, in which revision and language?
Packing and transportWhat is the stated delivery scope and named destination or handover point? Which transport services are priced?
Site workWho covers unloading, storage, access arrangements, building work and installation resources where required?
Installation and commissioningIs the offer for equipment supply, remote coordination, site attendance or a defined installation service?
Inspection and handoverWho coordinates local inspection, submissions and the agreed handover records?
Warranty and later supportWhat written terms, conditions, exclusions and support scope apply to this proposal?
Schedule and paymentWhich events start each period, what buyer inputs are needed, and which payment terms apply?

JAFITA states that installation, commissioning, local inspection and regulatory approval responsibilities should be defined before equipment supply. Its Installation Commissioning page also makes the support scope dependent on the actual project and agreement. Use that same level of specificity when comparing proposals.

Copy this record for each material requirement. Add supplier columns as needed.

Requirement / baseline referenceSupplier A: scope label and sourceSupplier B: scope label and sourceTechnical reviewOpen question / responsible party
Enter the requirement and revisionEnter the label and quotation page or clauseEnter the label and quotation page or clauseRecord the technical conclusion or pending reviewState what must be confirmed and by whom

Keep a separate commercial record alongside it:

ItemQuoted amount and currencyWhat the amount coversConfirmed additional costCost still unresolvedEvidence / revision
Enter the itemCopy the written amountDefine the priced boundaryEnter only a supported amountDescribe the unknown; leave it unpricedLink the supporting document

The source reference matters as much as the label. If a reviewer cannot locate the statement behind “included,” the row needs another look.

Two people wearing hard hats on a staircase at a construction site
Site coordination illustrates why a quotation comparison needs a clear owner for installation and project interfaces. Context image; not a quoted project.

Work through differences before choosing a total

Consider this hypothetical comparison. It illustrates how to use the worksheet; it is not a customer quotation or a JAFITA service offer.

ItemProposal AProposal BWhat the buyer should do
Drawing basisRefers to drawing R1Refers to drawing R2Ask the technical owner which revision is the comparison baseline and obtain confirmation of each proposal against it
Commissioning supportRemote support statedSite attendance stated; duration and covered activities unspecifiedRequest the exact activities, attendance basis and responsibilities before treating the services as equivalent
Installation laborExplicitly excludedNot mentionedRecord A as excluded and B as unspecified; establish who provides the required labor and obtain its scope

The remote-support and site-attendance offers may both be useful. They answer different project needs unless their scope is clarified. The worksheet should expose that choice rather than quietly treating the descriptions as interchangeable.

If an acceptable technical alternative is offered, keep it in a separate option comparison. Record its changed configuration, price basis, operational implications and required approvals. Do not replace the agreed baseline with the alternative without showing the change.

Keep unknown costs visible

An unspecified item has an unknown cost, not a zero cost. Likewise, an excluded item may still be required by the project even though it does not appear in the supplier’s total.

Keep the original quoted amounts intact. Add confirmed outside-scope amounts in separate rows, with their source and currency. If your team converts currencies for an internal comparison, state the chosen conversion basis and date, and retain the original amounts. Do not present an internal conversion as a revised supplier quotation.

Where required costs remain unresolved, label the result confirmed costs to date and attach the open-items list. Calling that figure the final installed cost would hide the remaining decisions.

Also check whether the quotations use comparable quantities, selected options and schedule assumptions. A price tied to a different quantity or an unconfirmed approval date should carry that condition into the review.

Send questions that can be closed in writing

Avoid sending a supplier a general request to “confirm everything is included.” Refer to a specific requirement, the relevant proposal text and the answer you need.

For the commissioning example, a useful clarification might read:

The proposal states site commissioning attendance. Please identify the activities included, the basis and duration of attendance, required site readiness, the local party responsible for the work, and any separately priced items. Please reference the quotation revision to which your answer applies.

Record the response against the original row. Where it changes scope, ask for the resulting commercial and technical documents to be aligned. Save the accepted revision alongside any earlier document that remains relevant to the decision record.

Clarification referenceRequirement and sourceQuestionOwnerAgreed response dateResponse / revised documentReview outcome
Assign a referenceIdentify the exact itemAsk for the missing decisionName the responsible partyRecord the agreed dateLink the response and revisionClosed, open or referred for technical review

Know when the comparison is ready for a decision

The comparison is ready for the responsible decision-makers when the material requirements have traceable answers, technical deviations have a recorded disposition, required work has an agreed owner, and remaining cost or schedule uncertainties are explicitly accepted or resolved.

An unanswered material question should remain visible. A supplier’s acknowledgement is not the same as confirmation of scope, and a procurement worksheet is not technical approval.

References and method notes

The sources below support the stated context and limits. The worksheets and hypothetical examples are editorial tools.